Sunday, September 14, 2025

Every Single F-35 Delivered To The US Military Last Year Was Late

 

                                                                              CLICK IMAGE TO ENLARGE

“TASK AND PURPOSE” By Matt White

“On average, new F-35s were delivered 238 days late in 2024. A government watchdog found that the Lockheed Martin continues to collect “hundreds of millions” in fees despite sagging delivery times. Current acquisition costs are $89.5 Billion more than 2012 Baseline Estimate.”

________________________________________________________________________________________________

“Every F-35 delivered to the U.S. military last year by Lockheed Martin was behind schedule by an average of seven months, a government watchdog found, but contractors kept millions in “incentive fees” designed to speed up the delivery.

To catch up, the aerospace giant now says it will “reduce the scope” of capabilities in new planes. 

The latest round of jets will now “cost $6 billion more and completion is at least 5 years later than original estimates,” a report by the Government Accountability Office found. “In 2024, Lockheed delivered 110 aircraft. All were late by an average of 238 days, up from 61 days in 2023.”

In a statement to Task & Purpose on the GAO report, a Lockheed Martin spokesperson said, “The F-35 is combat-proven, offers the most advanced capability and technology, and is the most affordable option to ensure America and its allies remain ahead of emerging threats.”

The F-35 has been slated to be the U.S. military’s primary modern strike and air superiority fighter since it was originally funded in 2001, and is — uniquely among strike aircraft — flown by all three fixed-wing air components. The Air Force took delivery in April of its 500th F-35, the Marines own about 250, and the Navy has over 100. Those totals are about one-third of the roughly 2,470 fighters the Pentagon plans to buy and fly for 77 years, according to the GAO.

But the program has been beset by cost overruns and delayed deliveries since its inception. The total cost of the full F-35 fleet was expected to be $233 billion when originally funded in 2001. By December 2023, that number had more than doubled to $485 billion.

The latest round of F-35s delivered in the last seven years and currently on order are known as Block 4 of the program. Block 4 jets, the GAO said, were meant to come equipped with “new weapons, radar enhancements, and technology to avoid aircraft collisions” and with new features that “address new threats that have emerged since DOD established the aircraft’s original requirements in 2000.”

But those enhancements, the GAO said, will now be scaled back.

“The program plans to reduce the scope of Block 4 to deliver capabilities to the warfighter at a more predictable pace than in the past,” the GAO said.

The specific list of Block 4 enhancements that will be scaled back will be finalized this fall, the GAO said. F-35 officials told the GAO that they will delay “some capabilities—including those that require an upgraded engine to function—to future modernization efforts. Program officials stated that they will also remove others that no longer meet warfighter needs.”

In its statement to Task & Purpose, Lockheed Martin said it “will deliver 170-190 F-35s this year and continue fielding Block 4 capabilities to ensure the F-35 maintains its unmatched dominance in the skies.” 

A screenshot from the GAO report showing delays in 2024 compared to previous years. Screenshot via Government Accountability Office.

Dan Grazier, a senior fellow and program director at the Stimson Center, has tracked the F-35 program for over a decade at government watchdogs. The admission that some Block 4 technology will be reduced “seems kind of innocuous, but is absolutely mind-blogging,” he said.

“[They] don’t go into what capabilities they’re shaving off the top, but I promise you, the capabilities that they aren’t going to deliver for the F-35 were the capabilities for which they sold the program in the very first place,” Grazier said. “The really high-end capabilities [are] what we’re really paying for when we’re paying this massive premium.”

Millions in fees for late deliveries

The GAO report also said Lockheed has collected “hundreds of millions of dollars” intended to reward quicker production for planes delivered late.

“The F-35 program’s use of incentive fees has largely been ineffective at holding the contractors accountable to delivering engines and aircraft on time,” the report found. “The F-35 program office compensated Lockheed Martin with hundreds of millions of dollars of performance incentive fees while the percentage of aircraft delivered late and the average days late grew.”

Through 2022, most F-35s were delivered by Lockheed Martin on time or with delays that averaged less than a month. But in 2023, 89 of 98 planes were late and in 2024, all 110 were late by an average delay of 238 days.

But as deliveries fell behind, the GAO found, F-35 officials adjusted the terms of the fees.

“Where the program originally tied incentives to on-time delivery, the program gave the contractor a second chance to earn fees by redirecting those incentives to other aspects of the program when it was clear that Lockheed Martin would not deliver any aircraft on time,” the GAO found.

Engine maker Pratt & Whitney also collected “tens of millions” in incentive fees despite late deliveries of the engines.

“This incentive structure and late delivery penalty was not effective at improving on-time deliveries,” the GAO said. “Unless the F-35 program reevaluates its use of incentive fees and better aligns them to achieving desired production schedule outcomes, it will be at greater risk of continuing to reward contractors for delivering engines and aircraft late.”

Every single F-35 delivered to the US military last year was late

ABOUT THE AUTHOR:



Matt Whit is a senior editor at Task & Purpose. He was a pararescueman in the Air Force and the Alaska Air National Guard for eight years and has more than a decade of experience in daily and magazine journalism. He also teaches news writing at the University of North Carolina-Chapel Hill’s Hussman School of Journalism and Media where he is frequently referred to as a “very tough grader” on Rate My Professor. You can reach Matt at matthew.white@taskandpurpose.com





Tuesday, October 01, 2013

"The Plane that Ate The Pentagon- The Politically Engineered F-35"

The F-35A at Eglin Air Force Base -"Vanity Fair"

"THE PROJECT ON GOVERNMENT OVERSIGHT (POGO)"

"In "Vanity Fair", Adam Ciralsky investigates the F-35 aircraft, or Joint Strike Fighter, that was meant to streamline and update the military’s fleet of planes. When Ciralsky first saw the jet he said he “didn’t know whether to genuflect or spit.”

The plane offers hopes of a futuristic military combat system with technologies far superior to what we have now. But it’s also seven years behind schedule and millions of dollars over budget. When first conceived in 2001, each F-35 was supposed to cost $81 million. In his piece POGO’s Winslow Wheeler puts the true cost of the airplane at $219 million or more per copy:


So what went wrong? In 2001, Lockheed Martin won a valuable government contract worth an estimated $233 billion to create the plane. Instead of testing the plane’s various aspects before production, Lockheed Martin decided to use a practice called concurrency–producing and testing the plane at the same time.

As of now, the planes can’t drop bombs and have only 2% of the necessary coding to be used in combat. During testing, pilots have ended up abandoning their futuristic helmets mid-flight due to the confusion they cause. The planes also can’t fly in inclement weather, something a  $60,000 Cessna can do.

Another basic question: why hasn’t the government stepped in to keep Lockheed Martin on track? Ciralsky believes it’s due to an expensive and brilliantly conceived manipulation of our political system.
The political process that keeps the Joint Strike Fighter airborne has never stalled. The program was designed to spread money so far and so wide—at last count, among some 1,400 separate subcontractors, strategically dispersed among key congressional districts—that no matter how many cost overruns, blown deadlines, or serious design flaws, it would be immune to termination. It was, as bureaucrats say, “politically engineered.
 POGO has reported on the problematic F-35 in the past. Recommendations include cancelling the more expensive and problematic variants of the F-35 and replacing them with proven, less expensive systems. Wheeler, though, believes the project should be abandoned all together. He wrote in Foreign Policy, “There is only one thing to do with the F-35: Junk it. America’s air forces deserve a much better aircraft, and the taxpayers deserve a much cheaper one. The dustbin awaits.”

Read the rest of the article in Vanity Fair to see how just how bad the F-35 program has become."